SNAG THOSE DEFECTS
1999 has been a bumper year so far for important new developments in building law, with disputes ranging from multi-million pound commercial contracts to minor residential works going before the courts.

Two developments which have particular significance for smaller contractors and sub-contractors are the enforceability of Adjudicators` decisions and the interpretation of "defects liability" provisions in the JCT Minor Works Contract.
Adjudication, introduced by the Construction Act 1996 has been with us for some time but it was until recently in doubt whether an Adjudicator`s decision could be enforced.   Adjudication is a "fast track" way of getting a decision on construction disputes (it only takes 28 days) and can be  used while the contract is still going on, instead of having to wait until the end to go to arbitration or the Court.   It is a particularly strong weapon for sub-contractors who are not being paid on time, or at all, by main contractors.   However, the government failed to put in  place any framework for forcing the main contractor to pay up following an Adjudicator`s decision and many contractors simply  assumed that they could ignore Adjudicator`s decisions against them.
In a recent case in which Macob Civil Engineering claimed to have been underpaid by £300,000 by Morrison Construction the Adjudicator decided that the mone had to be paid.   Morrison refused to pay and so Macob took the case to court.   The Senior Judge of the Technology and Construction Court, Mr Justice Dyson, ruled that the money had to be paid immediately.
As a result main contractors will now have to pay up on the Adjudicator`s decision.   They will still have the right to appeal against an adjudication by going to arbitration, or the Courts, once the contract has been completed, but the money must be paid to the sub-contractor in the meantime.   This decision by the Court should significantly ease the payment log jams which have caused many sub-contractors to go into insolvency.
Adjudication cannot, unfortunately, be used for residential works where the employer is the house owner.   Many disputes arise in this sector, and contractors received a setback from the Courts on the question of defects liability and release of retention.   In the case of Pearce and High-v-Baxter, the builder had completed works to a £35,000 extension under the JCT Minor Works Contract.   Practical completion was certified and the 6 month defect liability period went by.   At the end of this time, the retention money had not been paid and the builder sued.   The house owners said that there were outstanding defects, but the first Court to hear the matter held that, as they had raised  their complaint after the 6 month defects liability period had passed, the house owners were too late and had to pay the builder the retention money.   The house owners went to the Court Of Appeal which decided that the passage of the defects liability period does not mean that the house owner loses his right to sue for defects for all time.  During the defects liability period the contractor has the right to re-enter the property to put defects right at his own expense and the employer must reasonably let him back in again to do this.   However if, at the end of the period there are still outstanding defects, the house owner can still claim for defects.
The clear message to all contractors is to return to site and carry out all snagging works promptly.   However, there is still the risk that, if defects  appear after the 6 month liability period, the house owner can keep all, or part, of any retention.

The matter of retentions does not arise where a C.I.T.A. Warranty is placed on work, leaving the builder, and the client, secure in the knowledge that the work carries an insurance backed warranty.

Source: Morgan Cole Solicitors



Back To Construction Update IndexBACK TO MAGAZINE INDEX PAGEBack To Construction Update Index


HOMEBack to CITA Home PagePAGE